IOP Marina Public Dock and Greenspace
Milestone timeline:
On September 22, 2020, City Council voted to create a public dock and greenspace in the space formerly leased to the commercial watersports operation.
On November 2023, City Council awarded a contract to Truluck for the construction of a new public dock, which will include a 16' wide pier with covered area with benches and swings, a new floating dock with an ADA compliant gangway, kayak and stand-up paddle board launch.
Construction began on April 2024, and the anticipated completion date is June 1, 2024.
View the public dock design drawings here.
Project Funding Source:
$1.7M ($1M ARP, Marina Fund, Muni ATAX & State ATAX)
Project Updates
IOP Marina Public Dock & Greenspace
- Funding Source: $1.7M ($1M ARP, Marina Fund, Muni ATAX & State ATAX)
- Framing and decking work complete. Gangway being fabricated. Truluck and ATM finalizing floating dock submittal.
Technical workshop held in March to identify vulnerabilites and establish agreed upon sea level rise projections. Stakeholder meetings held w the Planning Commission and Enviromental Advisory Committee in May. Sea Level Rise Community Engagement Survey released in July and deadline is August 1.
IOP Marina Public Dock & Greenspace
- Framing and decking work in process. Gangway and floating dock submittals under review by ATM - once approved, will be released for fabrication. City waiting on revised completion schedule.
IOP Marin "T" Dock Repairs
- Completed
Marina Dredging - Design and Permitting
- Work in process. ATM coordinating pre-application meetings and coordinating w stakeholder groups that are considering joining City's permit application. Construction anticipated in FY26.
OP Marina Public Dock & Greenspace
- Funding Source: $1.7M ($1M ARP, Marina Fund, Muni ATAX & State ATAX)
- Pile driving and superstructure construction almost complete. Delay on the floating dock and ADA gangway submittals, due in part to challenges with confirmation of location of subaqueous electrical cable that runs from the IOP to Goat Island near proposed floating dock. Substantial completion date is June 16th but may be pushed.
IOP Marina "T" Dock Repairs
- Funding Source: $200K Marina Fund
- Repairs are near completion
IOP Marina Public Dock & Greenspace
- Funding Source: $1.7M ($1M ARP, Marina Fund, Muni ATAX & State ATAX)
- Demolition of public dock began week of 4/1. After demolition, contractor will begin pile driving. Anticipated completion June 1st.
IOP Marina "T" Dock Repairs
- Funding Source: $200K Marina Fund
- Work in progress
Marina Dredging - Design and Permitting
- Funding Source: $1.5M FY23 State Budget Allocation
- Work in progress. ATM coordinating pre-application meetings and coordinating w stakeholder groups that are considering joining City's permit application. Construction anticipated in FY26.
IOP Marina Public Dock & Greenspace
Contract executed with Truluck Construction. Construction drawings in process. Contractor anticipated to mobilize in March.
IOP Marina "T" Dock Repairs
Removal of electrical and water systems, repairs to fixed pier and floatind dock and installation of fire extinguisher pedestals included in Truluck contract. Tenants requested to extend finger piers in lieu of new electrical and water systems, which requires permit modification from regulatory agencies. ATM provided proposal to City for permit modification assistance and coordination.
Marina Dredging - Design and Permitting
In process. ATM coordinating pre-application meetings and coordinating w stakeholder groups that are considering joining City's permit application. Construction anticipated in FY26.