IOP Marina Public Dock and Greenspace
Milestone timeline:
On September 22, 2020, City Council voted to create a public dock and greenspace in the space formerly leased to the commercial watersports operation.
On November 2023, City Council awarded a contract to Truluck for the construction of a new public dock, which will include a 16' wide pier with covered area with benches and swings, a new floating dock with an ADA compliant gangway, kayak and stand-up paddle board launch.
Construction began on April 2024, and the anticipated completion date is June 1, 2024.
View the public dock design drawings here.
Project Funding Source:
$1.7M ($1M ARP, Marina Fund, Muni ATAX & State ATAX)
Project Updates
IOP Marina Public Dock & Greenspace
- Construction contract executed and kick off meeting to be held end of January. Estimated project completion in May 2024.
- Staff and ATM working on executing contract, then issue notice to proceed.
IOP Marina "T" Dock Repairs
- Budget for repairs approved by Council. Tenant feedback suggests a reallocation of funds away from replacing water and utility systems to extending finger piers. Permit modification required.
Marina Dredging
- In process. ATM, staff and marina tenants met in December to review scope and schedule. Also working with stakeholders who want to join City's permitting process.
IOP Marina Public Dock & Greenspace
Bid Package released on 10/19. Pre-bid meeting held on 11/1. Bid deadline
11/21.
IOP Marina "T" Dock Repairs
City received OCRM permit for minor repairs and maintenance for the "T" dock.
Scope of repairs included with the public dock project bid packet due 11/21.
Marina Dredging
In process. ATM completed the dredge disposal alternatives. Staff coordinating
progress meeting to review options and determine next steps in permitting
process.
Marina Public Dock & Greenspace
Permits from Ocean and Coastal Research Management (OCRM) and the U.S. Army Corps (USACE) of Engineers are on hand.
IOP Marina "T" Dock Repairs
City reapplying for OCRM permit for minor repairs and maintenance for the "T" dock. City will bid scope of repairs with the public dock construction. In process.
Marina Dredging
ATM studying dredge disposal alternatives and preparing permit application.
Public Dock & Greenspace
Design work 95% complete. Permits from OCRM and USACE are expected by the end of September. Bidding will quickly follow once permits are in hand.
T Dock Repairs
Repairs/Maintenance to the T dock to be included as an alternate bid with the public dock bidding process.
Dredging
City held stakeholder meeting on 8/23 to begin coordination with marina neighbors to join permitting and dredging efforts. ATM studying the dredge disposal alternatives.
Public Dock & Greenspace
• City needs to engage ATM for bidding and construction administration services.
• City and Islander 71 need to agree and finalize parking redesign plan for the north side of the boat ramp with the goal of eliminating
the shared lot and creating separate parking areas for the City/residents and restaurant patrons and finalize scope and design of the
greenspace along the landside of the boardwalk.
T Dock Repairs
Repairs/Maintenance to the T dock planned to be included as an alternate bid along with the public dock bidding process.
Dredging
Staff held kick-off meeting on July 18. First task involves local engagement and coordination with neighboring facilities on Morgan
Creek to identify their dredging needs and invite them to join City’s permitting efforts for potential cost and regulatory efficiencies.
Meeting with local stakeholders scheduled for mid-August.
Public Dock & Greenspace
• ATM finalizing dock design specifications for bidding. ATM seeking feedback from Council at the 7/11 workshop meeting.
• City and Islander 71 need to agree and finalize parking redesign plan for the north side of the boat ramp with the goal of eliminating the shared lot and creating separate parking areas for the City/residents and restaurant patrons and finalize scope and design of the greenspace along the landside of the boardwalk.
T Dock Repairs
Repairs to the T dock planned to be included as an alternate bid along with the public dock bidding process.
Dredging
Contract with ATM executed. Kickoff meeting scheduled for week of July 17.