Phase 3 Drainage Project - Outfalls & Basin
Milestone timeline:
The City has initiated the third phase of a project to improve storm water and tidal drainage across the island. This project is intended to make significant drainage improvements to the 30th, 36th and 41st Avenue outfalls which will improve conditions on the amount of standing water events experienced by residents and property owners.
The project began in 2017 when City Council tasked the Planning Commission with developing a strategy to address drainage problems. As part of the project, smaller but impactful drainage improvement projects along the basin will also be addressed. These are located at Sparrow Drive, Forest Trail, Cross Lane, 32nd Avenue and 41st Avenue.
The construction of the 30th and 36th Avenue outfalls began in early 2022 and expected completion in 2023. The construction of the drainage improvements to the 41st Avenue outfall is scheduled to begin in the fall/winter of 2023.
Project Updates
Phase 3 Drainage - 30th Avenue Outfall
- Complete
Phase 3 Drainage - 36th Avenue Outfall
- Complete
Phase 3 Drainage - 41st Avenue Outfall
- Project substantially completed. Final items include installation of handrail, trash racks and gates.
Phase 3 Drainage - 41st Avenue Outfall
- Funding Source: Capital Projects Fund Bond Proceeds
- 95% of pipe has been laid and construction continues on the headwall. Anticipated completion by end of May.
Phase 3 Drainage - 30th Avenue Outfall
- Funding Source: Capital Projects Fund Bond Proceeds
- Project complete
Phase 3 Drainage - 36th Avenue Outfall
- Funding Source: Capital Projects Fund Bond Proceeds
- Safety grates delivered
Phase 3 Drainage - 41st Avenue Outfall
- $3M SC Office of Resilience Grant. $29K (Permitting) + $61K (Additional Fill) + $479K (Pipe Extension) from Capital Projects Fund Bond Proceeds
- Construction work in progress. Closure of intersection of Waterway Blvd and 41st Ave planned for week of 4/8. Anticipated completion mid-May.
Waterway Boulevard Multi-Use Path Elevation Project
- Funding Source: $1.1M ( $157K Design & Permitting - Capital Projects Fund. City seeking $990K Grant from FEMA Hazard Mitigation Grant for construction)
- Design and engineering in process. T&H evaluating feasibility of increasing level of protection by elevating the path an additional foot. No update from SCEMD on FEMA Hazard Mitigation grant announcement.
Sea Level Rise Adaptation Plan
- Funding Source: $20K - Beach Preservation Fund
- Technical workshop held in March to identify vulnerabilites and establish agreed upon sea level rise projections. Stakeholder meeting scheduled w the Planning Commission and Enviromental Advisory Committee in May.
Phase 3 Drainage - 36th Avenue Outfall
- Work begins October 16th. Road closure scheduled for October 17th. Residents in the area have been notified of upcoming road closure
Phase 3 Drainage - 41st Avenue Outfall
- Contractor mobilized in January and began laying pipe at the intersection of Waterway Blvd and 41st Ave. Delays in dewatering work area due to tides/groundwater issues and coordination with Dominion Energy to hold power poles for stabilization.
Waterway Boulevard Multi-Use Path Elevation Project
- Design and engineering in process. No update from SCEMD on FEMA Hazard Mitigation grant announcement.
Sea Level Rise Adaptation Plan
- Technical workshop scheduled for end of February to identify vulnerabilities and establish agreed-upon sea level rise projections.
Phase 3 Drainage - 36th Avenue Outfall
Road work complete. Crews are on site. 3-4 weeks for substantial completion.
Phase 3 Drainage - 41st Avenue Outfall
- The Bastion Group under contract and mobilized week of January 2nd. Staff working with marina restaurant on temporary license agreement to allow construction access through the employee lot. Change order to extend pipe to the headwall provided for consideration.
Waterway Boulevard Multi-Use Path Elevation Project
- Thomas & Hutton under contract for design, engineering and permitting. Survey completed in 12/23. Waiting onfinal FEMA funding announcement.
Sea Level Rise Adaptation Plan
- Seamon Whiteside identified technical stakeholders group and scheduling meeting for late January 2024.
Phase 3 Drainage - 36th Avenue Outfall
- Road paved and reopened 11/3 after contractor completed stormwater and
utility work. Waiting on fabrication of steel reinforcement package (3-4 week
lead time). Contractor expected back on site first week of December and
substantial completion in January 2024.
Phase 3 Drainage - 41st Avenue Outfall
- SCOR in process of executing contract with The Bastion Group. Construction
scheduled to begin in January 2024.
Waterway Boulevard Multi-Use Path Elevation Project
- Legal reviewing contract language changes proposed by T&H.
Sea Level Rise Adaptation Plan
- Kickoff meeting held week of 9/25. Seamon Whiteside coordinating stakeholder meetings.