Phase 3 Drainage Project - Outfalls & Basin

Milestone timeline:

City Council tasks the Planning Commission with developing a strategy to address drainage problems.
Completed: Aug 22, 2017
2017
Planning Commission begins discussing the issues and meeting with experts regarding next steps.
Completed: Sep 20, 2017
September 20, 2017
Planning Commission concludes that the next stormwater priority should be to improve the outfalls between 30th and 41st Avenues.
Completed: May 9, 2018
May 9, 2018
After interviewing several firms the Planning Commission recommends that City Council Enter into an agreement with Thomas and Hutton.
Completed: Oct 11, 2018
October 11, 2018
City Council approves award of a contract to Thomas & Hutton in the amount of $100,800 for surveying, needs assessment and conceptual design of Phase III Drainage Project.
Completed: Nov 27, 2018
November 27, 2018
City Council approves a proposal from Thomas & Hutton for small but high impact drainage projects in the basin along the Phase 3 Drainage project area.
Completed: Mar 26, 2019
March 26, 2019
City staff presents proposal to improve five (5) drainage deficient areas located on the basin between 30th and 41st Avenue.
Completed: Jul 23, 2019
July 23, 2019
City Council approves change order from Thomas & Hutton for small but high impact drainage projects in Phase 3 and issues approval of design, engineering, and permitting of Phase 3 Drainage Project.
Completed: Aug 27, 2019
August 27, 2019
City Council approves proposal in the amount of $18,900 for a conceptual assessment of the elevation of the Waterway Boulevard path to provide added protection from rising tidal waters.
Completed: Jun 23, 2020
June 23, 2020
City Council approves FY21 budget including funding for the small but high impact drainage projects and construction of the Phase 3 Drainage Project.
Completed: Jun 23, 2020
June 23, 2020
City Council approves a change order in the amount of $30,000 for Thomas & Hutton to conduct bidding and construction administration services for the small but high impact drainage projects.
Completed: Jul 28, 2020
July 28, 2020
The City submits a grant application to the Rural Infrastruction Authority for grant funds towards the construction of Phase 3 Drainage Project.
Completed: Sep 14, 2020
September 14, 2020
The City advertises RFB 2020-06 seeking bids for the construction of the small but high impact drainage projects.
Completed: Sep 27, 2020
September 27, 2020
City staff will hold a pre-bid meeting with interested bidders to provide an overview of the project and answer questions.
Completed: Oct 8, 2020
October 8 2020
Deadline for submission of proposals for the construction of the 5 small but high impact drainage projects.
Completed: Oct 29, 2020
October 29 2020
Utility relocations begin
Completed: Mar 1, 2021
March 1 2021
Drainage pipe installation - 41st Avenue
Completed: Mar 15, 2021
Mid March
Drainage pipe installation - Sparrow DriveDrive
Completed: Apr 1, 2021
Early April
Drainage pipe installation - Forest Trail
Completed: Apr 15, 2021
Mid April
Drainage pipe installation - Cross Lane
Completed: Apr 29, 2021
End of April
Council approves change order to Thomas & Hutton to include bidding and construction oversight of the 30th & 36th Ave Outfall Projects.
Completed: Jul 27, 2021
Jul 27 2021
Bid packet for construction of 30th & 36th Ave Outfall is released to prospective bidders.
Completed: Sep 14, 2021
Sep 14 2021
City holds pre-bid meeting with prospective bidders for the construction of 30th & 36th Ave Outfall Projects.
Completed: Sep 24, 2021
Set 24 2021
Deadline for bids for the construction of the 30th & 36th Avenue Outfall Project.
Completed: Oct 15, 2021
Oct 15 2021
City opened bids for the construction of the 30th and 36th Outfalls
Completed: Nov 10, 2021
Nov 10 2021
City Council approves a contract to Quality Enterprise in the amount of $2.27M
Completed: Nov 17, 2021
Nov 17 2021

The City has initiated the third phase of a project to improve storm water and tidal drainage across the island. This project is intended to make significant drainage improvements to the 30th, 36th and 41st Avenue outfalls which will improve conditions on the amount of standing water events experienced by residents and property owners.

The project began in 2017 when City Council tasked the Planning Commission with developing a strategy to address drainage problems. As part of the project, smaller but impactful drainage improvement projects along the basin will also be addressed. These are located at Sparrow Drive, Forest Trail, Cross Lane, 32nd Avenue and 41st Avenue.

The construction of the 30th and 36th Avenue outfalls began in early 2022 and expected completion in 2023. The construction of the drainage improvements to the 41st Avenue outfall is scheduled to begin in the fall/winter of 2023. 

Project Updates

Update - June 2024
Tuesday, June 18, 2024

Phase 3 Drainage - 30th Avenue Outfall

  • Complete 

Phase 3 Drainage - 36th Avenue Outfall

  • Complete

Phase 3 Drainage - 41st Avenue Outfall

  • Project substantially completed. Final items include installation of handrail, trash racks and gates.
Update - May 2024
Tuesday, May 14, 2024

Phase 3 Drainage - 41st Avenue Outfall

  • Funding Source: Capital Projects Fund Bond Proceeds
  • 95% of pipe has been laid and construction continues on the headwall. Anticipated completion by end of May.
Update - April 2024
Tuesday, April 9, 2024

Phase 3 Drainage - 30th Avenue Outfall

  • Funding Source: Capital Projects Fund Bond Proceeds 
  • Project complete

 

Phase 3 Drainage - 36th Avenue Outfall

  • Funding Source: Capital Projects Fund Bond Proceeds
  • Safety grates delivered 

 

Phase 3 Drainage - 41st Avenue Outfall

  • $3M SC Office of Resilience Grant. $29K (Permitting) + $61K (Additional Fill) + $479K (Pipe Extension) from Capital Projects Fund Bond Proceeds
  • Construction work in progress. Closure of intersection of Waterway Blvd and 41st Ave planned for week of 4/8. Anticipated completion mid-May.

Waterway Boulevard Multi-Use Path Elevation Project

  • Funding Source: $1.1M ( $157K Design & Permitting - Capital Projects Fund. City seeking $990K Grant from FEMA Hazard Mitigation Grant for construction)
  • Design and engineering in process. T&H evaluating feasibility of increasing level of protection by elevating the path an additional foot. No update from SCEMD on FEMA Hazard Mitigation grant announcement.

 

Sea Level Rise Adaptation Plan

  • Funding Source: $20K - Beach Preservation Fund
  • Technical workshop held in March to identify vulnerabilites and establish agreed upon sea level rise projections. Stakeholder meeting scheduled w the Planning Commission and Enviromental Advisory Committee in May.
Update - February 2024
Tuesday, February 13, 2024

Phase 3 Drainage - 36th Avenue Outfall

  • Work begins October 16th. Road closure scheduled for October 17th. Residents in the area have been notified of upcoming road closure

Phase 3 Drainage - 41st Avenue Outfall

  • Contractor mobilized in January and began laying pipe at the intersection of Waterway Blvd and 41st Ave. Delays in dewatering work area due to tides/groundwater issues and coordination with Dominion Energy to hold power poles for stabilization.

Waterway Boulevard Multi-Use Path Elevation Project

  • Design and engineering in process. No update from SCEMD on FEMA Hazard Mitigation grant announcement.

Sea Level Rise Adaptation Plan

  • Technical workshop scheduled for end of February to identify vulnerabilities and establish agreed-upon sea level rise projections.
Update - January 2024
Thursday, January 11, 2024

Phase 3 Drainage - 36th Avenue Outfall

Road work complete. Crews are on site. 3-4 weeks for substantial completion.

Phase 3 Drainage - 41st Avenue Outfall

  • The Bastion Group under contract and mobilized week of January 2nd. Staff working with marina restaurant on temporary license agreement to allow construction access through the employee lot. Change order to extend pipe to the headwall provided for consideration.

 Waterway Boulevard Multi-Use Path Elevation Project

  • Thomas & Hutton under contract for design, engineering and permitting. Survey completed in 12/23. Waiting onfinal FEMA funding announcement.

 Sea Level Rise Adaptation Plan

  • Seamon Whiteside identified technical stakeholders group and scheduling meeting for late January 2024.

 

Update - November 2023
Tuesday, November 14, 2023

Phase 3 Drainage - 36th Avenue Outfall

  • Road paved and reopened 11/3 after contractor completed stormwater and
    utility work. Waiting on fabrication of steel reinforcement package (3-4 week
    lead time). Contractor expected back on site first week of December and
    substantial completion in January 2024.

 

Phase 3 Drainage - 41st Avenue Outfall

  • SCOR in process of executing contract with The Bastion Group. Construction
    scheduled to begin in January 2024.
  •  

Waterway Boulevard Multi-Use Path Elevation Project

  • Legal reviewing contract language changes proposed by T&H.

 

Sea Level Rise Adaptation Plan

  • Kickoff meeting held week of 9/25. Seamon Whiteside coordinating stakeholder meetings.

 

 

Pages