Phase 3 Drainage Project - Outfalls & Basin
Milestone timeline:
The City has initiated the third phase of a project to improve storm water and tidal drainage across the island. This project is intended to make significant drainage improvements to the 30th, 36th and 41st Avenue outfalls which will improve conditions on the amount of standing water events experienced by residents and property owners.
The project began in 2017 when City Council tasked the Planning Commission with developing a strategy to address drainage problems. As part of the project, smaller but impactful drainage improvement projects along the basin will also be addressed. These are located at Sparrow Drive, Forest Trail, Cross Lane, 32nd Avenue and 41st Avenue.
The construction of the 30th and 36th Avenue outfalls began in early 2022 and expected completion in 2023. The construction of the drainage improvements to the 41st Avenue outfall is scheduled to begin in the fall/winter of 2023.
Project Updates
Phase 3 Drainage - 30th Avenue Outfall
- Project has been completed.
Phase 3 Drainage - 36th Avenue Outfall
- Work begins October 16th. Road closure scheduled for October 17th. Residents in the area have been notified of upcoming road closure.
Phase 3 Drainage - 41st Avenue Outfall
- South Carolina Office of Resilience is in the process of executing a contract with The Bastion Group. Kick off meeting scheduled for the week of 10/9.
Waterway Boulevard Multi-Use Path Elevation Project
- Staff in process of executing contract with Thomas & Hutton for design, engineering and permitting, as approved by Council on 9/26.
Sea Level Rise Adaptation Plan
- Kickoff meeting held week of 9/25. Seamon Whiteside coordinating stakeholder meetings.
30th Avenue
- Project complete
36th Avenue (Forest Trail)
- Work begins the first week in October. Road closure is scheduled for October 4th. The estimated project duration is 8 weeks.
- See Latest News for road closure updates.
41st Avenue
- Deadline for Bids - 9/14
Waterway Boulevard Multi-use Path Elevation Project
- Two bids received. Staff coordinating with SCEMD for approval of contractor to perform pre-award costs for engineering and permitting. A recommendation for approval of contract will be made at the Council meeting on 9/26/23.
30th Avenue
- Contractor on site installing tide check valves, tide gates, trash racks and grates on the junction box.
36th Avenue (Forest Trail)
- Construction to start immediately following Labor Day weekend.
41st Avenue
- Pre-bid meeting – August 23, 2023. Deadline for bids– August 30, 2023.
Comprehensive Drainage Master Plan
- Davis & Floyd updating executive summary for report to be completed and distributed.
Waterway Boulevard Multi-use Path Elevation Project
RFP for design, permitting, bidding and construction administration is out. Deadline for proposals – August 18, 2023.
Waterway Boulevard Multi-use Path Elevation Project
- RFP for design, permitting, bidding and construction administration is out. Deadline for proposals – August 18, 2023.
Phase 3 Drainage 30th, 36th & 41st Avenue Outfalls 30th Avenue
- Check valves have been delivered and are on site. Castings and grates are in and waiting for fabrication of miscellaneous items (railings, trash racks, etc.) All installation to be completed at the same time with same crew.
36th Avenue (Forest Trail)
- Coordination and agreement on conceptual design of junction box complete. Construction of 36th Avenue outfall to start in the fall. 41st Avenue
- MS4, NPDES, OCRM, USACE & SCDOT permits on hand.
- Environmental Assessment completed and approval of grant funds for purchase of wetland credits approved
T&H prepared technical specifications and special provisions for bidding - Start of construction planned for fall/winter 2023.
Comprehensive Drainage Master Plan
- Maintenance review and development regulations review and recommendations in progress
- Waterway Boulevard Multi-use Path Elevation Project
- Staff developing Request for Proposals for the City to engage engineering firm to perform pre-award costs for engineering and permitting in accordance with FEMA’s Hazard Mitigation Grant Program specifications.
30th Avenue
• Still waiting on delivery of check valves. Castings and grates are in and waiting for fabrication of miscellaneous items (railings, trash racks, etc.) All
installation to be completed at the same time with same crew.
36th Avenue (Forest Trail)
• Coordination and design of junction box still in process. Construction of 36th Avenue outfall to start in the fall.
41st Avenue
• MS4, NPDES, OCRM, USACE & SCDOT permits on hand.
• Terracon coordinating purchase of mitigation credits and Environmental Assessment w/ SCOR
• T&H prepared technical specifications and special provisions for bidding
• Start of construction planned for fall/winter 2023.
30th Avenue
• Check valves in final stage of production. Expected to arrive in 2-3 weeks.
36th Avenue (Forest Trail)
• Coordination and design of junction box still in process. Construction of 36th Avenue outfall to start mid-August
41st Avenue
• MS4, NPDES, OCRM & USACE permits on hand. SCDOT encroachment permit still in review.
• Terracon coordinating purchase of mitigation credits and Environmental Assessment w/ SCOR
• T&H prepared technical specifications and special provisions for bidding
• Start of construction planned for end of 2023