The City and Dominion Energy entered into an agreement for the design, engineering and construction of undergrounding utility projects.
The following projects have been identified by the City as priorities:
- 21st Avenue and Palm Boulevard
- IOP Marina
- End of 41st Avenue
- 14th Avenue
- Palm Boulevard and Oak Harbor (11th and 13th Avenue)
Updates
21st Avenue Update - April 2023
Monday, April 10, 2023
Project complete.
• Staff will hold meeting with Dominion Energy on 4/12
to review list of remaining projects and identify
others for consideration.
21st Avenue Update - October 2022
Monday, October 10, 2022
- City executed construction agreement with Dominion Energy
- SCDOT encroachment permit on hand
- Dominion Energy waiting on easement from the Methodist Church
- Still on track for construction this fall
21st Avenue Update - August 2022
Monday, August 22, 2022
- City executed construction agreement with Dominion Energy
- SCDOT encroachment permit on hand
- Still on track for construction after Labor Day.
- Tentative project schedule – Late September to early October.
21st Avenue Update - July 2022
Monday, July 11, 2022
- City executed construction agreement with Dominion Energy
- SCDOT encroachment permit on hand
- Still on track for construction after Labor Day
21st Avenue Update - June 2022
Monday, June 20, 2022
- City executed construction agreement with Dominion Energy
- DE preparing SCDOT encroachment permit for submittal
- Construction scheduled for fall/winter of 2022.
21st Avenue Update - May 2022
Monday, May 16, 2022
- City received revised construction agreement. New regulation that requires DE to dispose mud created from boring activities increased cost estimate by $7,000.
- Construction scheduled for fall/winter of 2022.
21st Avenue Update - April 2022
Monday, April 18, 2022
- Feasibility study and construction estimates complete. Estimate for construction is $65,000.
- City would contribute 50% of the total of the construction using the Non-Standard Service Fund.
- If the work outlined in the project scope exceeds the estimated costs, there will not be additional charges to the City. If there are unforeseen issues not outlined in the scope, the City would be notified of additional costs, also split 50/50.
- Dominion Energy provided a construction agreement for the City to execute. Once executed, DE can begin scheduling the construction of the project for the fall/winter of 2022.
21st Avenue Update - March 2022
Monday, March 14, 2022
- Dominion Energy received final drawings from contractor and is working on preparing packet to submit to SCDOT for the encroachment permit.
- Contractor requested lane closures during construction; Dominion Energy working on traffic control plans.
- City’s share of construction (50%) included in FY23 Capital Plan. Construction slated for Fall/Winter 2022.
21st Avenue Update - February 2022
Monday, February 14, 2022
- Dominion Energy very close to having bore profiles for the SCDOT permit and final design drawings
Bore profiles have not been completed yet. Necessary for final design and final construction estimate. - A bore profile is a drawing that shows the depth of the new conduit being installed relative to the existing utilities and ensures that there is a good enough window for this conduit to be drilled in without damaging any of the other existing utilities.
- City’s share of construction (50%) included in FY23 Capital
Plan. Construction slated for Fall/Winter 2022.
21st Avenue Update - January 2022
Monday, January 17, 2022
- Dominion Energy very close to having bore profiles for the SCDOT permit and final design drawings.
- A bore profile is a drawing that shows the depth of the new conduit being installed relative to the existing utilities and ensures that there is a good enough window for this conduit to be drilled in without damaging any of the other existing utilities.