The City and Dominion Energy entered into an agreement for the design, engineering and construction of undergrounding utility projects.
The following projects have been identified by the City as priorities:
- 21st Avenue and Palm Boulevard
- IOP Marina
- End of 41st Avenue
- 14th Avenue
- Palm Boulevard and Oak Harbor (11th and 13th Avenue)
Updates
Update - October 2021
Monday, October 18, 2021
City and Dominion Energy agreement and design/engineering estimates for the proposed projects:
21st Avenue at the intersection with Palm Boulevard ($10,000)
- Agreement executed. Design and engineering in progress
End of 41st Avenue from Waterway Boulevard to the IOP Marina ($15,000)
- Engineering scope includes assessment of relocation of transformer by the boat ramp and new lighting layout for the site
Design & engineering completion estimated 3-4 months from agreement execution.
The total cost of the projects and construction timelines will be determined when the design & engineering work is complete.