Isle of Palms Marina Dock Rehabilitation

Milestone timeline:

City Council approves contract to Applied Technology Management (ATM) for design, engineering &permitting of dock rehab
Completed: Aug 28, 2018
Aug 28 2018
City Council approves conceptual design for the dock repairs
Completed: Jan 22, 2019
Jan 22 2019
City receives permit from the Office of Ocean & Coastal Resource Management (SCDHEC-OCRM)
Completed: Jan 13, 2020
Jan 13 2020
City receives permit from the US Army Corps of Engineers (USACE)
Completed: May 25, 2020
May 25 2020
City Council approves FY21 budget which includes a bond issue of $2.9M for the construction of the dock project
Completed: Jun 23, 2020
Jun 23 2020
City completes and releases bid package to competitively procure a contractor to perform the dock project
Completed: Jul 10, 2020
Jul 10 2020
Staff holds a Pre-Bid meeting at the IOP Marina to meet contractors, answer questions and walk the project site
Completed: Jul 28, 2020
Jul 28 2020
Deadline for submission of proposals
Completed: Sep 3, 2020
11:00 a.m., September 11, 2020
Ways and Means Committee recommends award of a contract to Salmon's Dredging Co. for the project
Completed: Sep 15, 2020
Sep 15 2020
City Council approves contract for Salmon's Dredging and Corporation in the amount of $4,304,008
Completed: Sep 22, 2020
Sep 22 2020
City hosts Pre-Construction Meeting with key stakeholders to discuss schedule and other considerations
Completed: Oct 20, 2020
Oct 20 2020
City Council approves additional provision for Builder's Risk
Completed: Oct 27, 2020
Oct 27 2020
Contractor begins cleaning and re-coating work on the bulkhead.
Completed: Nov 17, 2020
Nov 17 2020
City Council approves change order from Salmons Dredging for Fuel Hut
Completed: Feb 23, 2021
Feb 23, 2021
Demolition of Dock Area "C" begins
Completed: May 10, 2021
May 10, 2021
Design work for fuel hut completed
Completed: May 10, 2021
May 15, 2021
Installation of new docks begins in Dock Area "C"
Completed: Jun 4, 2021
May 24, 2021
Installation of utilities in Dock Area "C" begins.
Completed: Jun 4, 2021
June 4, 2021
Restaurant and Face Docks are turned over to Marina Operator for use.
Completed: Sep 14, 2021
Sep 14 2021
Salmons Dredging begins demolition of Dock Area "B" Charter Docks
Completed: Sep 23, 2021
Sep 23 2021
Construction complete. All systems 100% functional
Completed: May 31, 2022
May 31 2022

In 1999, the City of Isle of Palms purchased the marina facility located at the confluence of Morgan Creek and the Atlantic Intracoastal Waterway. The floating docks at the marina are approximately 30-year old timber framed docks. 

The FY21 Budget includes funds to replace the aging docks, including the fuel dock, fuel hut and marine utility infrastructure, located along Morgan Creek. This project also includes needed maintenance for the bulkhead.

The project involves the construction of Phase I and Phase II of the approved conceptual plan of the dock improvement project. 

The City expects to award a contract by the end of September and construction to begin after September 30, 2020. The project is expected to take approximately 5-6 months to complete.  

 

Project Updates

Marina Dock Rehab Update - May 2022
Tuesday, May 17, 2022
  • Construction complete. All systems 100% functional
  • SCDHEC permit for potable water system on hand
  • 2 windows for hut expected this month
  • As-builts and warranty package preparation underway
Marina Dock Rehab Update - April 2022
Tuesday, April 19, 2022
  • Walk-through inspection for substantial completion was held on Friday, April 15.
  • Potable water system passed the pressure test last week. First bacterial sample was taken yesterday by the testing lab, and it passed. Second sample was taken this morning and results are expected tomorrow. When the second bacterial test passes, SCDHEC will issue permit for water to be used for drinking.
  • Fire suppression stand-pipe system was tested las week, but it was noted there was a small drip at one of the electro-fuse couplings at a transition in Charter docks. Replacement fittings were ordered last Friday will be picked up today and installed tomorrow.
  • Sewer pump-out system installed and plumbed. The section of line between the pump and the bulkhead will be pressure tested tomorrow.
  • Electrical panels will be opened for detailed inspection followed by discussion regarding the warranty.
  • Salmons will touch up the coating on the bulkhead where the fire suppression feed lines transited through the bulkhead.
  • Transworld will repour two sections of tabby sidewalk in the path where electrical conduits were installed.
  • Salmons is assembling as-builts, Operations & Maintenance manual, warranty statements for all components furnished for the project.
Marina Dock Rehab Update - March 2022
Tuesday, March 15, 2022
  • Fuel dock- working on fuel dispensing, water, and fire suppression systems. Power and fire pedestal installed.  
  • Fuel hut- close to complete; working on cabinets, interior and exterior finishes.
  • Charter docks- close to complete; working on water and fire suppression systems.
  • Restaurant and face docks- the power supply for the docks has been interrupted twice in the last month, but both were by design and caused by potentially unsafe conditions.
  • Expect to be complete by April 1st, except water certifications by DHEC and as-built documentation.
Marina Dock Rehab Update - February 2022
Tuesday, February 15, 2022
  • Work on final phase is ongoing Fuel dock and fuel hut
  • Fuel dock is fully installed, and fuel hut construction is underway. Structure is fully framed and dried in, interior utility routing is nearly complete.
  • ATM, EPIC, Salmons, Petroleum Marine and marina operator met on site last week to review and discuss the installation of the fuel system for the dock ( Routing, dispenser placement, sump access, fuel system control wiring in the fuel hut, fuel cost displays, etc.)
  • Salmons, EPIC, ATM, and the marina operator reviewed and confirmed power and fire pedestal placement on the fuel dock. This will allow for the installation of these items.
  • All previously reported problems with the electrical system on the Charter Docks have been corrected via pedestal re set process that is printed on the pedestal. Salmons reviewed this process with the marina operator for future reference.
  • The Restaurant and Face Docks have been energized. The panel that previously failed in this area will be monitored and tested over the next few weeks to ensure proper performance.
  • Salmons is actively working to engage their mechanical sub contractor to complete the water and fire protection installation on the Fuel Dock. This work will be scheduled once the power pedestals are installed.
  • ATM installed of grip tape at the end of the gangways to address slipping concerns.
Marina Dock Rehab Update - January 2022
Tuesday, January 18, 2022
  • Builders Risk extended through March 2022
  • Restaurant & Face dock electrical panel issues:
  • The replacement breaker is in hand and ready to be installed.
  • When Transworld went to install replacement breaker some unusual, pre-mature corrosion was discovered on several other parts within the distribution panel. These parts have been ordered for replacement to quickly get power back to these docks. Contractor monitoring electrical panel to identify root cause of corrosion. No obvious signs of moisture within the unit.
  • City expressed concerns over these issues and the new system’s long-term reliability. Contractor and engineer working with subcontractor on solutions to ensure system is reliable.
  • Engineer & contractor evaluating various solutions to address tripping hazards with the metal plates at the end of the gangways
  • Fuel hut:
  • Roof, windows and doors to be installed by the end of this week
  • Electrical rough-ins completed
  • Completion scheduled end of this month
  • On-going coordination with subcontractor who will install fuel dispensers and fuel system – Complete installation scheduled for the end of February.
Marina Dock Rehab Update - November 2021
Wednesday, November 17, 2021
  • Supplemental floats to fix freeboard issue on the Restaurant dock expected by the end of 11/15 week.
  • City evaluating timing of potable water hook up for Charter Docks.
  • We can hook up the potable water now, do the testing, coordinate with DHEC, etc. for an extra fee of ~$10,000.
    Potable water would be operational by mid December OR we can wait and hook up the potable on Charter and Fuel at the same time for no extra fee. All of this probably will be done mid to late January.
  • Salmon’s Dredging waiting on two (2) additional loads from Structure Marine:
    • The first load includes the fuel docks and the angle bracket for the corner of Charter down by the boat ramp. This load is on a truck in route to SC.
    • The second load includes the fuel dock platform and will be shipped by the week of 11/22.