Isle of Palms Marina Dock Rehabilitation

  1. Aug 28 2018
    City Council approves contract to Applied Technology Management (ATM) for design, engineering &permitting of dock rehab
    Aug 27, 2018
  2. Jan 22 2019
    City Council approves conceptual design for the dock repairs
    Jan 21, 2019
  3. Jan 13 2020
    City receives permit from the Office of Ocean & Coastal Resource Management (SCDHEC-OCRM)
    Jan 12, 2020
  4. May 25 2020
    City receives permit from the US Army Corps of Engineers (USACE)
    May 24, 2020

In 1999, the City of Isle of Palms purchased the marina facility located at the confluence of Morgan Creek and the Atlantic Intracoastal Waterway. The floating docks at the marina are approximately 30-year old timber framed docks. 

The FY21 Budget includes funds to replace the aging docks, including the fuel dock, fuel hut and marine utility infrastructure, located along Morgan Creek. This project also includes needed maintenance for the bulkhead.

The project involves the construction of Phase I and Phase II of the approved conceptual plan of the dock improvement project. 

The City expects to award a contract by the end of September and construction to begin after September 30, 2020. The project is expected to take approximately 5-6 months to complete.  

 

Updates

No project items have been added.