Waterway Blvd Multi-Use Path Elevation Project

Funding Source:

$1.1M ( $157K Design & Permitting - Capital Projects Fund. City seeking $990K Grant from FEMA Hazard Mitigation Grant for construction)

Updates

Update - March 2025

Monday, March 10, 2025
  • Staff has learned that golf course ownership has concerns about the project and does not want to participate.
  • Staff and engineer are working directly with the contractor to determine if the project can be done without working through the golf course contract. City attorney is working with the owners' attorney to find solutions that would appease concerns.
  • If solutions can be developed, additional work will be necessary to create easements for long term maintenance of the flood controls.

Update - February 2025

Monday, February 10, 2025
  • Staff has learned that the change the scope of the project to increase the level of protection from 6’ to 7’, has been escalated from the State to FEMA for review. The grant consultant indicates that the State felt that the increase in protection should not negatively impact the grant award.
  • Staff, engineer and Wild Dunes staff are working to develop an agreement to incorporate flood mitigations modifications into the planned golf course improvements as approved by Council in January. Work could begin before the end of February. Additional work is happening to create an easement for long term maintenance of the flood controls.

Update - January 2025

Monday, January 13, 2025
  • Staff met with grant coordinator and learned that the change the scope of the project to increase the level of protection from 6’ to 7’, has been escalated from the State to FEMA for review. Staff is working with City’s grant consultant to understand the implications.
  • Staff and engineer are working with Wild Dunes staff and Wild Dunes golf course contractor to finalize a cost estimate to incorporate flood mitigations modifications into the planned golf course improvements. The staff is hopeful to have a range of cost by workshop meeting and a detailed estimate for full Council meeting.

Update - September 2024

Monday, October 07, 2024
  • Staff met with FEMA and executed the grant agreement. FEMA advised on necessary next steps to change the scope of the project to increase the level of $1.1M ( $157K Design & Permitting - Capital Projects Fund. City seeking $990K Grant from FEMA Hazard Mitigation Grant for construction) Waterway Boulevard Multi-Use Path Elevation Project protection from 6’ to 7’, which is being worked on now with the City’s grant consultant.
  • Staff, engineer , Wild Dunes staff, and Wild Dunes golf course contractor met on site to discuss the incorporating flood mitigations modifications into the planned golf course improvements. The golf course contractor is working on providing a cost estimate to incorporate the flood mitigation into the project.

Update - August 2024

Monday, August 12, 2024

T&H anticipates finalizing the design and initiate the permitting process in September. FEMA announced award of approx. 1M grant for project.