Sea Level Rise Adaptation Plan
Milestone timeline:
Technical Workshop Held in March
March 2024
Funding Source:
$20K - Beach Preservation Fund
Project Updates
Update - February 2025
Tuesday, February 11, 2025
- The revised plan was provided to the City and the consultant is scheduled to present the plan at the March workshop.
Update - January 2025
Tuesday, January 14, 2025
The revised plan has provided to the City and the consultant is scheduled to present the plan at the February or March workshop.
Update - September 2024
Tuesday, October 8, 2024
- A draft of the plan has been reviewed by staff, the Planning Commission and the Environmental Advisory Committee. Comments have been provided back to the consultant and they are incorporating comments into the draft. A revised draft should be presented to Council within the next month.
Update - August 2024
Tuesday, August 13, 2024
Technical workshop held in March to identify vulnerabilites and establish agreed upon sea level rise projections. Stakeholder meetings held w the Planning Commission and Enviromental Advisory Committee in May. Sea Level Rise Community Engagement Survey released in July and deadline is August 1.