Phase 4 Drainage - Palm Boulevard b/t 38th and 41st Avenue
Milestone timeline:
City Council Approves Funding
April 2024
The City has initiated the fourth phase of a project to improve stormwater and tidal drainage across the island. This project is intended to make significant drainage improvements to Palm Boulevard, between 38th and 41st Avenue.
Funding Source:
Estimated $2M. Capital Projects Fund and FY25 State budget allocation
Project Updates
Update - August 2024
Tuesday, August 13, 2024
Design in process. T&H preparing to submit for permits in several weeks. Permits on hand projected by end of 2024/early 2025.
Update - June 2024
Tuesday, June 18, 2024
City awarded contract to Thomas & Hutton for the design, engineering and permitting.